Masjid Project

LAND PURCHASE, PHASE ONE CONSTRUCTION

Our Site-Plan Documents have  been submitted to the City of Oshawa Planning Department for approval. 

Once our Site-Plan Documents are aproved, we will be requried to submitt our Detailed Construction Drawings which provide the details required for our construction team to begin construction. 

We have twelve months from the date of purchace (February 28, 2025), to begin construction.  

We kindly request your continued support, cooperation and prayers.  

Please see chart below for total Pre-Construction cost that were paid in full on February 28, 2025:

Land Purchase

$475,000.00

Letter of Credit
(To the City of Oshawa)

$237,500.00

City of Oshawa
Legal Fees

$27,007.00

D.G. Biddle & Associates
Site Plan / Zoning By-Law          

$47,800.00

Cambium Inc.
Geotechnical Investigation /
Hydrogeological Assessment

$28,718.00

KAD Lank Surveying Inc.
Topographical Survey /
Land Registry Deposit

$6,158.50

HKLA Landscape Architects
Landscape Plan

$3,390.00

Renor and Associates Inc.
Architectural Drawings

$3,164.00

YCA Engineering Ltd.
Noise Study

$2,260.00

Total Pre-Construction Cost:

$830,997.50